Shipbuilding Contract: Standard Templates, Critical Clauses, Negotiation
For a newbuild yacht or ship, the main contract is the shipbuilding contract. While Saleform / MOA is used for second-hand purchases, newbuild uses SAJ, NSF Newbuilcon or BIMCO Newbuildcon templates. This guide walks through the structure and negotiation points.
What this guide covers
- The structure of a newbuild contract
- Standard templates (SAJ, NSF Newbuilcon, BIMCO Newbuildcon)
- Critical clauses — spec, milestone payments, penalty clauses
- Refund guarantee, performance guarantee
- Negotiation pressure points
Note: This page is educational. It is not a substitute for legal advice — for a project-specific contract, your legal counsel and financing advisor must work side by side.
Standard templates
Three main templates on the newbuild side:
1. SAJ Form (Shipbuilders' Association of Japan)
- The most widely used template
- Originated from Japanese yards, but adopted globally
- Slightly more balanced toward the yard
- Detailed milestone payment structure
2. NSF Newbuilcon (Norwegian Shipbuilding Contract)
- Norway-based
- Slightly more balanced toward the owner
- Common across European yards
3. BIMCO Newbuildcon
- Published by BIMCO in 2007
- A modern alternative
- Designed to be balanced for both owner and yard
- Some clauses defined more clearly
On the yacht side: SAJ or a project-specific custom contract is most common. Superyacht projects often use custom drafting (every project differs).
Core structure
A shipbuilding contract typically contains the following sections:
1. Definitions + parties
- Owner + Builder (Yard) identities
- Vessel description (hull number)
- Reference documents (spec, GA drawings)
2. Description of the vessel
- Specification document reference
- Class society + flag determined
- Main dimensions + parameters
- Standard vs. optional systems
3. Price + payment structure
- Contract price
- Currency (typically € or $)
- Milestone payments + triggers
- Late payment penalties
4. Delivery + sea trial
- Target delivery date
- Sea trial procedure + acceptance criteria
- Late delivery penalty (liquidated damages)
- Owner's right to cancel (if late delivery cap exceeded)
5. Performance guarantees
- Speed guarantee (e.g. service speed in kn)
- Fuel consumption guarantee
- Deadweight / cargo capacity (commercial ship)
- If guarantee fails: liquidated damages
6. Variation orders (spec change)
- Variation order procedure
- How the price impact is calculated
- Delivery date impact
- Approval process
7. Inspection + class society
- Owner's right of inspection (owner's representative)
- Class society surveys
- Steps requiring prior approval
- Yard's obligation on rejected work
8. Refund guarantee + performance guarantee
- Refund guarantee terms
- Identity of the issuing bank
- Guarantee amount + scope
- Performance guarantee (if any)
9. Force majeure + suspension
- Force majeure definition
- Notification procedure
- Right to time extension
- Termination right on long suspension
10. Risk transfer + insurance
- Period during which risk sits with the yard (until delivery, typically)
- Builder's risk insurance requirement
- Owner's right to coordinate insurance
11. Warranty period
- Typically 12–24 months post-delivery
- Warranty scope (structural defects, system defects)
- Excluded scenarios
- Warranty claim procedure
12. Arbitration + governing law
- Dispute resolution seat (typically London LMAA)
- Governing law
Critical clauses — what to watch
Refund guarantee chain
Each milestone payment exposes the owner to yard risk. Refund guarantee terms:
- Issuing bank: local to the yard, or international?
- Amount: paid milestone + interest, or principal only?
- Call conditions: under what circumstances can the owner call?
- Tenor: does it renew with each milestone?
A weak clause → if the yard fails, the owner loses money.
Late delivery penalty (liquidated damages)
- Daily / weekly penalty amount
- Cap (e.g. 5% of contract price)
- Owner's cancellation right beyond the cap
- Force majeure time extension
Performance guarantees
- Speed measurement procedure (test conditions must be explicit)
- Fuel consumption measurement procedure
- Margin (e.g. 3% deviation tolerance) defined
- If guarantee fails: refund or compensation?
Variation order structure
- Can the owner change spec at any point?
- Price impact: transparent yard calculation?
- Delivery date impact automatic, or negotiated?
- Can the yard reject a variation?
Negotiation — who wants what?
Owner typically wants:
- Lower milestone payments (cash flow comfort)
- Higher refund guarantee amount
- Strong performance guarantees
- Clear spec compliance standards
- Broad inspection rights
Yard typically wants:
- Higher milestone payments (cash flow)
- Lower performance penalties
- Flexibility on variation orders
- Broad force majeure definition
- Short warranty period
Negotiation finds the middle. An experienced broker / legal counsel manages the process.
Coordination with the financing process
Points where the shipbuilding contract meets the financing side:
- Drawdown conditions — the bank's milestone-disbursement conditions are tied to the contract triggers
- Refund guarantee assignment — refund guarantee is typically assigned to the bank (collateral)
- Owner's representative report — the bank wants this before every drawdown
- Class society survey — the bank also tracks this
- Delivery clauses — the bank's drawdown timing must align with the contract delivery clauses
FAQ
Who drafts the shipbuilding contract?
Typically the owner's legal counsel prepares the draft (off a standard template), the yard side revises, and negotiation proceeds. Experienced yacht lawyers exist on the yacht side; maritime law specialists on the commercial ship side.
SAJ or NSF — which one?
Depends on the yard's geography. Asian yards know SAJ; European yards know NSF. BIMCO Newbuildcon is a modern alternative for both. A standard template is the starting point — project details get layered on top.
Can a newbuild contract be signed without a refund guarantee?
Practically no — too risky for the owner. Possible on small projects, but mandatory in projects with professional financing.
Can variation orders increase the price significantly?
Yes — a common surprise. This is why finalising the spec before contract signature + transparent variation order procedures are critical. Owner asks for a change, yard quotes, owner accepts, then it's signed.
What does the warranty period cover?
Typically: structural defects, main engine defects, system defects (under normal use). Excluded: wear and tear, normal damage, owner misuse, third-party damage.
Related
- New Build & Shipyard Financing — pillar
- Newbuild phases
- Construction milestone financing
- Refund guarantee
Talk to us about your project: let us plan the shipbuilding contract negotiation + financing coordination together. Reach out via the contact form.
